Hello,
I have the following scenario:
I have 6 pcs physical available of Item A on location X with profile 1. I have settings for that item, that I am allowed to put 2 pallets of the item in each location of the same profile 1. The conversion for Item 1 is 1 pallet = 10 pcs.
I also have automatic wave demand replenishment set up.
I have a SO for 12 pcs. I create wave, process it and AX creates replenishment work for 1 pallet to location X. So now, the future onhand on that location should be 6 + 10 = 16 pcs. I still don't complete the work.
Then I have another SO for 1 pcs. I create the wave and process it, and I expect, that AX will 'see', that I will have enough quantity at location X (6 physical available + 10 ordered - 12 on order = 4). But AX creates another replenishment work for 1 pallet to location Y (which is of the same profile 1). And if I have a third SO for another 2 pcs, the same happens - a third replenishment work for another full pallet.
Is there a setup, that i'm missing to prevent that unwanted behavior?
Thank you very much