Cost on completion basis.

$
0
0

Hi All,

In AX 2012 R2, I have the following requirement.

I created a project for which i have posted a PO of Amount USD 10000. I "Generate Committed cost", while calculating estimates i can see the whole PO cost.

But my billing rule is on "Percentage completion"

In Manual calculation field i specified only 10% and i want system to take only the 10% cost not the whole amount i.e. i want system to take only 10% of USD 10000 which is = USD 1000.

Because I am going to generate revenue on the monthly basis and if i post the whole cost together, then for the first month system will not show me the accurate revenue.

Can someone guide me to achieve this scenario in standard.

Thanks in advance,

Kind Regards,

Gaurav Chandak