Hello,
I have a problem with put-away works, when I split the original work.
Here are my setups in Menu item "Group put away"
The setting "Allow splitting of work" is activated.
I have an open work for put-away and it is for LP *4589, as you may see below
I have to pick 8 pcs. In mobile portal, I scan the LP id, hit button Full and register only 6 pcs to pick.
Now AX reduces the quantity of the existing work to 2 pcs, then creates another work for 6 pcs and creates a new target LP. This means, I take 6 pcs from the original LP and put them on a new (target) LP.
The problems is, that the 2 pcs, that I left on the original LP, are not there anymore! The LP is deleted from the work header. Now there is now way to finish this work - I have to cancel it and start over.
Is this a bug or am I missing a setup. Any help appreciated.
Thank you,
Ventsislav