I want to prepare next year production plan for product A from sales forecast:
01.2016 700 pcs.
02.2016 800 pcs.
All needed set up for run forecast scheduling are done. My forecast plan have Coverage time fence = Capacity time fence = 730.
Then demand forecast lines had been created: (date format: M/D/YYYY)
After run forecast schedule, there are only planned order of 2015. two planned orders of 2016 are miss.
Could you please tell me what are problems?