Quantcast
Channel: Microsoft Dynamics AX Forum - Recent Threads
Viewing all articles
Browse latest Browse all 72043

Parallell production orders in Dynamics AX 2009

$
0
0

In several of the operations in our factory, we would like to schedule parallel production orders. Take for example an oven. The oven is loaded with items from different production orders. The oven is started and after 10 hours, all production orders are ready at the same time. How should this be set up in AX? The operation should be scheduled to start and end at the same time for multiple production orders.


Viewing all articles
Browse latest Browse all 72043

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>