Hello everybody!
I would like to know if it is possible, and where-how to work this situation in AX 2012.
I have a resource group of 5 resources, a production order was scheduled to be finished by the 5 resources, but when I'm about to start the order, for whatever reason it is decided that this particular order will be produced using only 3 of the 5 resources.
Therefore I should have those 3 resources occupied longer time, and the other two free of capacity if nothing else is assigned to them.
What should I do to reflect this in AX?
Many thanks!
Héctor