Hi All
I have a question related to the item cost, actually we are in the business of making the readymix (Concrete) and we are using production module with little customization which is, when we end the production order packing slip of the sales order get generated automatically.
My Question here is, i checked the production order of item A, the cost of the production order is showing "2,580.12" and when i see the packing slip voucher it is showing "2,715.32", i think it should be same. I think the production item cost is coming from the Raw material and when we create the packing slip it is taking the average running cost of the finish good.
Please advise