AX2012 - an issue with production planning...

$
0
0

Hi Everybody,

Did anybody has tried to solve the following planning issue:

1. Company has two production sites: Site A and Site 2

2. Company produces Product in the following way:

a) Operations 10 to 40 can be done either in Site A or in Site B - there is no limits where

b) Operations 50 to 70 can be done ONLY in Site A.

Of course Client expects that:

a) AX will plan Productions taking first free resources for operations 10 to 40 either from Site A or Site B

b) there is no rules talking that production started in Site B MUST be continued in Site B

In summary - production could be done for example in that way:

Op 10     Site B

Op 20     Site A

Op 30     Site A

Op 40     Site A

OP 50 - 70 Site B

I will be very glad for any ideas....

Witold Adamiak