Hello guys,
We have updated to Dynamics AX 2012 R3 CU12 from Dynamics AX 2012 R3 CU10 two weeks ago and since then our Planning department has complained about the Master Planning functionality. It seems like it doesn't explode the item in sub levels meaning that it doesn't create the planned orders as expected. When we use Explode manually it works fine. It explodes the item with all expected sub levels. We haven't changed any of the settings from the old version. Is it a matter of settings or it is some kind of bug? Has anyone seen this before? Any info would be greatly appreciated. Thank you!