I create a project quotation in AX2012R3. I create a WBS with several activities for hour activities, assing the corresponding category but in the line details I update the sales and cost prices to new values.
I transfer the estimates to the quotation lines, send for approval, approve, confirm and transfer to the the project. When I review the WBS and check the sales and costs prices I see that the ones from the quotation have not been transfered and I have the predefined ones for the project category.
-Is this the standard way AX works?
-Is possible to setup not to update the WBS info?
-Should I create the project, create the prices for the project and after transfer to work with the WBS prices?
-What is the reason for this way of working?
Thanks in advance