Hi All,
I am facing a issue while posting a project invoice proposal.
This transaction is timesheet transaction.
- The issue says Business Unit should be filled.
- Talking about Account structure, I have kept a combination of Main Account --> Cost Center --> Business Unit.
- The Allow blank values is not checked.
- Also, the project which I have selected has all the values and system is taking cost center from the project dimensions only.
- Even the Business Unit is filled in project, it is trying to take from related project contract.
- Also, when I select a Business Unit value in Project contract, the proposal gets posted smoothly.
Reason I can't select BU in Project contract is because under same project contract we can have multiple projects, these projects can have different BU.
Kindly give me your feedback and suggestions.
Thanks for all the help!!