How do you use activities to correctly identify cost in AX Lean Module. Example: Simple machined part, machine time is 200 seconds and is needed to block out the appropriate time in the schedule, labor per part is 30 seconds. Currently the way I do costing I use the 200 seconds x Labor Rate ($10/hr) = .55 cents. I think this is incorrect and I should only be costing the 30 seconds - where in the setup do I identify the 30 seconds of labor but leave the 200 seconds for scheduling?
↧