Hi All,
One of my client has a production configuration like below:
1- There is work center P1 used for painting and it paints 1000 pcs /hour. (Defined capacity batch on work center as 1000 and finite capacity)
2- I have two production orders for same Item X and same qty: 200 pcs and this item uses painting work center in its production route.
3- For route of Item X, I have defined Formula field as "Workcenter batch qty"; Factor as "1"; Run time as "1"; Hours as 1. What I want to mean is in 1 hour I can paint 1000 pcs on workcenter P1.
4- When I run job scheduling by combine two production order together, system create two jobs sequencally, Job 1 starts and end 09-10 am, Job 2 starts and end 10-11 am.
5- What I want is due to my workcenter can produce 1000 pcs / hr , My production orders total 200+200= 400 < 1000 so, I want to see to create job orders on same start and end time Like job 1 09-10 am, and job 2 is also 09-10 am Simultaneous. What should I set up to achive this scenario?